To export your tasks and resources as CSV, open your Project on the Microsoft Project desktop and check if you have permission to perform this action. If you can’t save files in a CSV format, here’s what you need to do:

  • Press the “File” option, and then go to the “Options” dialog tab. The tab redirects you to “Project Options”.

Microsoft Project Desktop

Microsoft Project Desktop Sidebar

  • Under the “Project Options” tab, press the “Trust Center” option.

Project Options

  • Click on the “Trust Center Settings” button which leads you to the “Legacy Formats” tab.
  • Choose the “Allow loading files with legacy or non-default file formats” option and press “Okay”.

Trust Center

After you’ve changed the settings, return to the “Home” tab and choose “Export”:

  • Choose the “Save Project as File” option.

Project Export

  • After that, under “Project File Types” select “Project” and press the “Save as” button.

Save Project As

  • Define the file location and save it as type “CSV” (comma delimited) (*. CSV).

Save File As CSV

  • Press the “Save” button.

As soon as you’ve pressed the “Save” button, Export Wizard will open automatically. Here you need to do the following steps:

  • Click the “Next” button to continue.

Export Wizard

  • Choose “New map” to create your data settings from scratch and press “Next” again.

Export Wizard

  • Select the types of data you want to export: tasks or resources. Then click “Next”.

Export Wizard Options

Note: Microsoft Project allows exporting one type of data at a time, so you’ll need to run two exports.

  • Choose the needed fields.
Before formatting your data into a CSV file, ensure you have included all the required and optional fields for tasks and resources. This will ensure that your data is properly organized and that all necessary information is included for each task and resource.

What fields are required and what fields are optional when preparing a CSV file of tasks?

You can download the sample CSV file for task fields and modify it by adding your own data.

HeaderFormatField
ID1Required
NameSchedule kick-off meetingRequired
StatusOpenRequired
Priority500Optional
Resource_NamesSarah JohnsonRequired
NotesWe need to investigate this case as quickly as possibleOptional
CreatedYYYY-MM-DD HH:MM:SSRequired
Start_DateYYYY-MM-DD HH:MM:SSOptional
Finish_DateYYYY-MM-DD HH:MM:SSOptional
DeadlineYYYY-MM-DD HH:MM:SSOptional

You can download the sample CSV file for resources fields and modify it by adding your own data.

HeaderFormatField
NameSarah JohnsonRequired
Email_Addresssarah@yourcompanydomain.comOptional

Export Wizard Task

  • Then press the “Finish” button to save the files.

If you can’t install Microsoft Project Desktop, export your tasks and resources as CSV from Microsoft Project Online. Check out this guideline to learn how to do it. If something wasn’t clear enough, or you’d like to get into more details, feel free to contact our support team for help.